Significant progress has been made on the LIRR Expansion Project from Floral Park to Hicksville, one of the region’s most noteworthy transportation projects. While the duration and intensity of work depends on the project element under construction, the 3rd Track Constructors team is phasing elements to reduce the amount of disruption in any given community at any given time.
During the month of May, you will see crews performing the following construction activities in New Cassel:
Wall Construction
- Retaining and sound wall installation is finishing up on the north side of the tracks in New Cassel, from Sylvester Street to the Wantagh State Parkway.
Utilities
- Crews from EJ Electric have begun the process of removing temporary utility poles across the entire project alignment.
- In some areas, workers may have to access private property in which case the project will coordinate in advance with individual business/property owners.
3rd Track Construction
- Crews from J-Track will continue installing the third track ties and rails from Urban Ave to Hicksville.
Landscaping
- With planting season underway, 3TC has remained committed to landscaping and other design elements – such as the planting of trees, shrubs, and other greenery – that will enhance a completed project element and contribute to the beautification of the corridor.
Nassau 3 Interlocking, Signal and Divide 1 System
- The new system is a necessary component of a comprehensive modernization effort to streamline operations, optimize flexibility, and ensure the safe movement of trains along the corridor.
- Crews have begun removing and installing the Divide 1 switches. For more information regarding this work and its impacts, please see the following notice from the MTA.
Double Track Outages and Weekend Work
For Commuters:
Both tracks on the Mainline will be out of service on Saturdays from 1:17 am to Mondays at 2:27 am on the following, upcoming weekends:
- May 14-15
- May 21-22
Please visit the MTA Planned Service Page (https://new.mta.info/) to plan your trip
For residents living along the ROW:
Throughout the month of May, crews are working along the right-of-way on the weekends. Although work will be intensive along the corridor from Floral Park to Hicksville, consolidating the work timeframe will minimize impacts to commuters and the surrounding communities, ultimately reducing the need for invasive trackwork for years to come.
- On the weekends of May 14-15 and May 21-22 (Fridays at ~9:00 PM to Mondays at ~5:00 AM) crews are working along the right-of-way. Intensive work will occur between Urban Ave in New Cassel & Charlotte Ave in Hicksville.
- Please note that the LIRR and project team are utilizing upcoming DTO weekends to complete other necessary rail infrastructure upgrades along the corridor.
** There are no double-track outages or intensive work occurring during Mother’s Day, Memorial Day, the Belmont Stakes, or Father’s Day/Juneteenth weekend **
Additional LIRR Work Along the Railroad Right-of-Way
- In addition to the activities described above, you may see or hear LIRR forces working along the railroad right-of-way at various times during the month.
- To avoid LIRR service interruptions during peak commuting hours, LIRR work along the railroad right-of-way may be taking place overnight and on weekends.
- For more information, visit the post in the Community News section of LIRRExpansion.com.