Significant progress has been made on the LIRR Expansion Project from Floral Park to Hicksville, one of the region’s most noteworthy transportation projects. While the duration and intensity of work depends on the project element under construction, the 3rd Track Constructors team is phasing elements to reduce the amount of disruption in any given community at any given time.
During the month of January, you will see crews performing the following construction activities in Mineola:
Completion dates are subject to change due to developments related to COVID-19
Mineola Station Enhancements
- Foundations, columns and retaining wall installation will continue on the north and south sides of the tracks through January.
- Crews are working on the overpass building, on both the north and south sides of the tracks
- Work on the support building is continuing on the north side of the tracks
- EJ Electric is working on the installation of conduit, signage bands, and light fixtures on both the north and south sides of the tracks
- The Mineola Station House interior and exterior renovations are ongoing
Walls
- Crews will continue installing sound wall panels East of Herricks Rd to approximately Mineola station.
G16 Substation
- 3TC and EJ Electric are continuing to install necessary utilities to feed the new substation
- EJ Electric will be installing utility poles around the new and old substation this month
- Work will take place during the weekdays
- The G16 Substation is one of several substations along the Main Line being replaced or modified with new modern equipment.
3rd Track Installation
- Crews are continuing to install ballast from Willis Ave to Glen Cove Road on the south side of the tracks to prepare for the future installation of third track
- Once complete, crews will begin the installation of the third track
LIRR Work Along The Right of Way
- In addition to 3TC’s activities, you may see or hear LIRR forces working along the railroad right-of-way
- To avoid LIRR service interruptions during peak commuting hours, LIRR work along the railroad right-of-way may take place overnight and on weekends
- For more information, visit the post in the Community News section of LIRRExpansion.com
Nassau 3 Interlocking
- Crews are continuing to install signal cable for the New Nassau 3 Interlocking & Signal System from Roslyn Road to the Glen Cove Road along the right of way on the north side of the tracks
- On the weekend of January 29-30, there will be a Double Track Outage on the Main Line in support of New Nassau 3 Pretesting. Continue to the Double Track Outage section below for additional information.
Upcoming Double Track Outages
- On January 15-16, in support of a switch removal in Queens Interlocking, both main tracks on the Hempstead Branch will be out of service.
- Buses will replace train service at Bellerose Station and between Stewart Manor and Hempstead on the Hempstead Branch. Regularly scheduled Hempstead Branch Trains will depart Atlantic Terminal making stops at Nostrand Avenue, East New York, Jamaica, Hollis, Queens Village, Floral Park and then will proceed via the Main Line to Mineola Station where customers will detrain for bus service to all stations between Stewart Manor and Hempstead. Customers at Bellerose Station will be accommodated by buses to/from Queens Village Station for train service.
- On January 22-23, in support of a switch removal in Queens Interlocking, both main tracks on the Main Line will be out of service between New Hyde Park and Hicksville.
- Extra trains will be added between Hempstead and Penn Station to serve as an alternative service option for customers traveling to/from New Hyde Park, Merillon Avenue, Mineola, Carle Place, and Westbury.
- Bus service will be provided for Mineola customers between Mineola and Hempstead for connections to and from points west.
- Bus service will also be provided between Mineola and Hicksville.
- On January 29-30, in support of signal testing, both main tracks on the Main Line will be out of service between Mineola and Hicksville.
- As an alternative, additional service will be provided on the Hempstead Branch on a half-hourly basis.
- Buses will replace train service between Mineola and Huntington.
- For up-to-date LIRR service changes, please visit https://new.mta.info/alerts