Significant progress has been made on the LIRR Expansion Project from Floral Park to Hicksville, one of the region’s most noteworthy transportation projects. While the duration and intensity of work depends on the project element under construction, the 3rd Track Constructors team is phasing elements to reduce the amount of disruption in any given community at any given time.
During the month of January, you will see crews performing the following construction activities in Carle Place:
Completion dates are subject to change due to developments related to COVID-19
Wall Construction
- Crews substantially completed restoring Atlantic Avenue on the north side of the tracks between the Meadowbrook Parkway and Cherry Lane Bridge.
- A dedicated landscaping area has been constructed along the wall and landscaping has been installed in most of the available areas. In the spring of 2022, 3TC will return to the area to finish the wall in its permanent condition and maintain newly planted greenery
G17 Substation
- Following the successful delivery and installation of the G17 Substation, 3TC and EJ Electric will continue to work on the necessary electrical components which feed the substation
- The G17 Substation is one of several substations along the Main Line being replaced or modified with new modern equipment.
Carle Place Station Enhancement
- 3TC, EJ Electric and various subcontractors will continue performing finish work in and around the Carle Place Station
- 3TC has completed the modification of the Garden Ave ramp, ensuring ADA accessibility
LIRR Work Along The Right of Way
- In addition to 3TC’s activities, you may see or hear LIRR forces working along the railroad right-of-way
- To avoid LIRR service interruptions during peak commuting hours, LIRR work along the railroad right-of-way may take place overnight and on weekends
- For more information, visit the post in the Community News section of LIRRExpansion.com
Upcoming Double Track Outages
- On January 15-16, in support of a switch removal in Queens Interlocking, both main tracks on the Hempstead Branch will be out of service.
- Buses will replace train service at Bellerose Station and between Stewart Manor and Hempstead on the Hempstead Branch. Regularly scheduled Hempstead Branch Trains will depart Atlantic Terminal making stops at Nostrand Avenue, East New York, Jamaica, Hollis, Queens Village, Floral Park and then will proceed via the Main Line to Mineola Station where customers will detrain for bus service to all stations between Stewart Manor and Hempstead. Customers at Bellerose Station will be accommodated by buses to/from Queens Village Station for train service.
- On January 22-23, in support of a switch removal in Queens Interlocking, both main tracks on the Main Line will be out of service between New Hyde Park and Hicksville.
- Extra trains will be added between Hempstead and Penn Station to serve as an alternative service option for customers traveling to/from New Hyde Park, Merillon Avenue, Mineola, Carle Place, and Westbury.
- Bus service will be provided for Mineola customers between Mineola and Hempstead for connections to and from points west.
- Bus service will also be provided between Mineola and Hicksville.
- On January 29-30, in support of signal testing, both main tracks on the Main Line will be out of service between Mineola and Hicksville.
- As an alternative, additional service will be provided on the Hempstead Branch on a half-hourly basis.
- Buses will replace train service between Mineola and Huntington.
- For up-to-date LIRR service changes, please visit https://new.mta.info/alerts