Floral Park
Significant progress has been made on the LIRR Expansion Project from Floral Park to Hicksville, one of the region’s most noteworthy transportation projects. While the duration and intensity of work depends on the project element under construction, the 3rd Track Constructors team is phasing elements to reduce the amount of disruption in any given community at any given time.
During the month of January, you will see crews performing the following construction activities in Floral Park:
Completion dates are subject to change due to developments related to COVID-19
Floral Park Station Enhancement Project
- This month, crews will continue the process of commissioning and testing the new Floral Park Station elevators to ensure complete functionality and safety requirements are met
- Temporary platform barricades will be removed once the elevators have been completed
- Elevators will be ADA-compliant and will provide easier access to the platforms on both sides of the station
- The elevators are expected to be open for public use in early 2021
Wall Construction
- Wall construction is underway along the Hempstead Branch, from Tunnel Street heading east into the retention basin along the north side of the tracks.
- This retaining wall is being installed to support new railroad switches on the Hempstead Branch
- These switches will allow trains to move from track to track more easily
- In adherence to our commitment to minimize disruption to the community, noise, dust, and vibration are continuously monitored
Permanent Utility Pole Installation
- Permanent wooden utility poles have been installed along the railroad right-of-way from Plainfield Avenue to Covert Avenue
- Crews will begin to safely relocate cables from temporary poles to permanent poles
- Once utility lines have been relocated, temporary utility poles will begin to be removed throughout the Village of Floral Park
- Intermittent lane closures may be necessary in order to facilitate this work
- Heavy construction equipment including cranes, bucket trucks, and more, are needed for this work
- Once utility lines have been relocated, temporary utility poles will begin to be removed throughout the Village of Floral Park
LIRR Work Along the Railroad Right-of-Way
- In addition to 3TC’s activities, you may see or hear LIRR forces working along the railroad right-of-way. These activities may include:
- Regular track inspection and maintenance; rail tie replacement; grade crossing elimination preparatory work
- To avoid LIRR service interruptions during peak commuting hours, LIRR work along the railroad right-of-way may take place overnight and on weekends
- For more information, visit the post in the Community News section of LIRRExpansion.com
For up-to-date service changes and/or changes to station access, please visit MTA.info/LIRR