Garden City & Garden City Park
Significant progress has been made on the LIRR Expansion Project from Floral Park to Hicksville, one of the region’s most noteworthy transportation projects. While the duration and intensity of work depends on the project element under construction, the 3rd Track Constructors team is phasing elements to reduce the amount of disruption in any given community at any given time.
During the month of July, you will see crews performing the following construction activities in Garden City and Garden City Park:
Completion dates are subject to change due to developments related to COVID-19
New Hyde Park Road Grade Crossing Elimination Project
DOUBLE TRACK OUTAGE July 11 – 12
- During the weekend of July 11-12, a double track outage on the LIRR’s Main Line will allow the existing tracks to be demolished, and the newly built U-structure, which supports a new steel track bed, will be jacked into place using a box-jacking method previously used at Covert Avenue and Urban Avenue
- Train service will be suspended between New Hyde Park and Hicksville during this time. For up-to-date service information please visit MTA.info/LIRR
- The newly constructed bridge will hold three tracks, along with a five-lane grade-separated underpass, pedestrian sidewalks on the east and west sides of the roadway, as well as a dedicated left-turn lane from southbound New Hyde Park Road onto Clinch Avenue
- Plaza Avenue, between Herkomer Street and New Hyde Park Road, has been realigned to become a two-way street, and regraded to meet the new roadway
- A new signal is being installed at the New Hyde Park Road and Plaza Avenue intersection to assist with the flow of traffic
- The new surface lot at 115 New Hyde Park Road is nearly complete. Parking lot striping will occur in anticipation of the reopening of New Hyde Park Road
- For the remainder of the closure, signage and detour plans are in place throughout the area. Click here to see the vehicular detour map, and here to see the pedestrian detour map. To access the temporary NICE Bus route, please click here
- New Hyde Park Road is expected to be open by Labor Day
Merillon Avenue Station Enhancement
- Commuters will notice brick work occurring on multiple station elements including the new ADA-compliant elevators and the platform canopies
- Interior finishes for the north support building will be installed throughout the month of June
- Please board and exit all trains (westbound and eastbound) from the first six (6) cars at Merillon Avenue Station and continue to utilize the temporary crosswalks along Main Avenue
- Some parking spots will remain unavailable at Merillon Avenue; replacement parking is provided north of Merillon Avenue Station, along Broadway between County Courthouse Road and Herricks Road, on the south side of the street
Permanent Utility Pole Installation
- Crews from EJ Electric will continue to work during the day and overnight relocating cables from temporary poles to the permanent wooden and steel utility poles along the railroad right-of-way
- Heavy construction equipment including cranes, bucket trucks, and more, are needed for this work
- 3TC is contractually committed to performing ongoing environmental monitoring including air quality, vibration levels, and noise levels
- For more information on this project element click here
New Hyde Park Station Enhancement Project
- Crews are continuing the progression of platform canopies on the north and south sides of the tracks through the month of July.
- These canopies with be enclosed with brick once they have been erected
- Work is expected to commence on the New Hyde Park Station house towards late July
- Enhancements on this project element are being closely coordinated with the Village of New Hyde Park
- Construction is continuing on the south support building, which is necessary for the maintenance of the new station
- On the north and south side of the tracks, the walls of the South 12th Street Underpass have been formed with concrete. Future work will connect the pedestrian underpass underneath the tracks.
- Residents will see crews working both on weekends and overnight hours to meet the expedited construction schedule for this crucial project element.
- In adherence to our commitment to minimize disruption to the community, noise, dust, and vibration are continuously monitored
- Commuters will continue to access a temporary 10-car platform, which runs along 2nd and 3rd Avenues, between South 12th Street and South 8th Street
- For the remainder of the work, signage and detours are in place to help customers access the station. Click here to view the LIRR notification with a map of the new temporary station and here to see the pedestrian detour map. For a map of the temporary parking, click here, and here to see the temporary NICE Bus route
Wall Construction
- Sound wall installation on the south side of the tracks is progressing from New Hyde Park Road heading east toward Tanners Pond Road
- Residents along Greenridge Avenue will see crews performing work along the right-of-way for the duration of this activity
- 3TC construction teams are substantially complete with the installation of retaining and sound attenuation walls from Tanners Pond Road to Herricks Road
- In adherence to our commitment to minimize disruption to the community, noise, dust, and vibration are continuously monitored
LIRR Work along the Railroad Right-of-Way
-
- In addition to 3TC’s activities, you may see or hear LIRR forces working along the railroad right-of-way. These activities may include:
- Regular track inspection and maintenance; rail tie replacement; grade crossing elimination preparatory work
- To avoid LIRR service interruptions during peak commuting hours, LIRR work along the railroad right-of-way may take place overnight and on weekends
- For more information, visit the post in the Community News section of LIRRExpansion.com
- In addition to 3TC’s activities, you may see or hear LIRR forces working along the railroad right-of-way. These activities may include:
For up-to-date LIRR service changes and/or changes to station access, please visit www.MTA.info/LIRR and for up-to-date NICE Bus information, please visit www.nicebus.com