The LIRR Expansion Project from Floral Park to Hicksville, one of the region’s most significant transportation infrastructure projects, is now underway throughout the communities along a nearly ten mile stretch of mainline track.
The duration and intensity of work depends on the project element under construction. The project elements are phased to reduce the amount of disruption in any given community at any given time.
During the month of June, you will see crews continuing heavy construction activities in Floral Park, along with crews performing surveys, testing, ongoing rodent control, and monitoring construction activities for noise, dust, and vibration. By way of explanation:
South Tyson Viaduct Expansion
- The 3TC construction team and their associated contractors continue to make progress on this element of the LIRR Expansion Project – with 75 percent complete through the end of May
- Phase 3 of 4 of this project element – on the east side of South Tyson Avenue – continues, with construction crews:
- Installing rebar and pouring concrete for the bridge foundation
- The 18 “interior” parking spaces and the six parking spaces along the east side of the street, under the viaduct, remain unavailable for use
- Temporary alternate parking, with lighting, is available at 50 Carnation Avenue, with entrance off of Lily Street
- The construction team will provide cones, flagmen and signage at the work site to minimize interruptions and to direct pedestrian and vehicular traffic
- In coordination with the Village, and in an effort to make the area easier to navigate, additional crossing guards will be provided
Wall Construction
- Along Terrace Avenue, beginning at Plainfield Avenue, sections of the prefabricated wall will be installed
- Support of Excavation:
- Soldier piles and sheet piles are installed by vibratory hammers to provide the support necessary for the construction of the retaining wall
- Sections of soldier piles and sheet piles will be installed in sequence to form a wall for earth support
- Construction crews will also install tiebacks on the south side to anchor the retaining walls
- Crews will utilize western-most ballfield (The Pit) and the Village of Floral Park DPW yard for staging and accessing the LIRR right-of-way
- Wall Construction:
- Various machinery will be working along the right-of-way
- Daily delivery of the prefabricated wall to the Floral Park DPW yard
- Support of Excavation:
- In adherence to our commitment to minimize disruption to the community, noise, dust, and vibration are continuously monitored
Work along the Railroad Right-of-Way
- Excavation and installation of soldier piles, which will be installed in sequence to form a wall for earth support for work in and around the Floral Park substation
- In addition to 3TC’s activities, LIRR forces will be working along the railroad right-of-way
- To avoid LIRR service interruptions during peak commuting hours, LIRR work along the railroad right-of-way may take place overnight and on weekends
- These activities are ongoing across the Main Line corridor, and may include: regular track inspection & maintenance, rail tie replacement, and grade crossing elimination
- For more information, visit the post in the Community News section of LIRRExpansion.com